ANALISIS PENYIMPANGAN ANGGARAN PROYEK MENGGUNAKAN PERT DAN CPM (STUDI KASUS PADA PT ARION INTAN JAYA)

Authors

  • Putri Fortuna Nainggolan Fakultas Ekonomi, Universitas Katolik Santo Thomas Medan
  • Jonner Pangaribuan Fakultas Ekonomi, Universitas Katolik Santo Thomas Medan

DOI:

https://doi.org/10.54367/jimat.v1i1.1812

Keywords:

Budget, PERT, CPM

Abstract

This study aims to analyze the causes of deviations in the project budget of Rp. 103,249,432.15 and the delay of time for 2 weeks in the clean water pipe installation project in Aek Najaji Village, Padang Sidempuan Batunadua District. This research was conducted at PT Arion Intan Jaya for the period March-July 2019. The data analysis technique used was descriptive analysis technique using Planning, Evaluation and Review Technique (PERT) and Critical Path Method (CPM). The results showed that the high budget deviations and project time delays occurred due to rocky soil excavation activities, HDPE pipe installation and pipe stockpiling carried out per kilometer, from KM-1 to KM 6.5. The sequence of activities that are not suitable, causes a waste of time and variable labor costs as well as fixed costs. The total budget allocated for manpower is Rp. 456,435,000.00 for an implementation period of 150 days and the total realized labor cost is Rp. 522,745,000.00 with a project completion time of 164 days. If a review of critical activities is carried out using PERT and CPM, the project completion time changes to 96 days with a total cost of Rp. 413,760,000.00. So there is a decrease in the budget of Rp. 42,675,000.00.

Author Biography

Putri Fortuna Nainggolan, Fakultas Ekonomi, Universitas Katolik Santo Thomas Medan

Dosen

References

Adisaputro, Gunawan dan Marwan Asri. 2013. Anggaran Perusahaan. Edisi Kedua. Yogyakarta: BPFE.

Agyei, W. 2015. Project Planning And Scheduling Using PERT And CPM Techniques With Linear Programming: Case Study. International Journal Of Scientific & Technology Research. Vol 4(08); 222-227).

Diponegoro, Ahmad, dkk. 2018. Evaluasi Proyek Pembangunan Stone Crusher Machine Dengan Metode PERT/CPM di Malimping, Lebak, Banten. Penelitian Kolaboratif Dosen dan Mahasiswa (PKDM). Jakarta: Program Pascasarjana Manajemen Universitas Muhammadiyah Prof. Dr. Hamka.

Frederick dan Gerald. 1990. Pengantar Riset Operasi. Terjemahan Gunawan, Ellen dan Ardi Wirda. 1994. Jakarta: Erlangga.

Halim, Tjahjono. 2000. Sistem Pengendalian Manajemen. Edisi Revisi I. Yogyakarta: YKPN.

Handoko, T. Hani. 1987. Dasar-dasar Manajemen Produksi dan Operasi. Jakarta: BPFE.

Hansen dan Mowen. 2001. Akuntansi Manajemen Biaya. Jilid 2. Jakarta: Erlangga.

Herjanto, Eddy. 1999. Manajemen Produksi dan Operasi. Jakarta: PT. Grasindo.

Horngren, Charles, T. 2012, Akuntansi Biaya. Jilid 1. Edisi ke 12. Jakarta: Erlangga.

Shim, Jae K and Joel G. Siegel. 2008. Financial Management. Barron Education Series Inc, New York.

Jay dan Barry. 2008. Manajemen Operasi. Terjemahan Sungkono, Chriswan. 2009. Jakarta: Salemba Empat.

Mulyadi. 2001. Akuntansi Manajemen. Cetakan Pertama. Jakarta: Salemba Empat.

Munandar. 2001. Budgeting. Yogyakarta: BPFE.

Munandar, Abdul Haris. 2019. Analisis Network Planning Dengan CPM (Critical Path Method) Dalam Rangka Efisiensi Waktu dan Biaya Pada Manajemen Proyek Pembangunan Drainase Kecamatan Tambun. Skripsi. Bekasi: Fakultas Ekonomi Bisnis dan Ilmu Sosial Universitas Pelita Bangsa.

Rayburn, Letricia Gayle. 1996. Akuntansi Biaya: Menggunakan pendekatan Manajemen Biaya. Terjemahan Sugyarto. 1999. Jakarta: Erlangga.

Sharma, J.K. 2001. Quantitative Techniques for Managerial Desicion. India: Macmillan Publishers India Limited.

Siswanto. 2007. Operations Research. Jakarta: Erlangga.

Sugiyono. 2014. Metode Penelitian Pendidikan Pendekatan Kuantitaif, Kualitatif dan R & D. Bandung: Alfabeta.

Downloads

Published

2022-03-25

Issue

Section

Articles